EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

SR 80 (Southern Blvd) Bridge Replacement Project

Home / FAQs

FAQs (Frequently Asked Questions)

Will construction affect vehicular and boat traffic?
The project team will work to minimize impacts to both vehicular and marine traffic during construction. In order to maintain two lanes of traffic over the Intracoastal Waterway, a temporary bridge will be built adjacent to and on the north side of the existing bridge. Traffic will be shifted onto the temporary bridge as the old bridge is demolished and the new bridge is built on that alignment. Traffic will be moved onto the new bridge when completed and the temporary bridge will be removed.

When the Tidal Relief bridge is replaced the traffic will be shifted to the south side of the existing bridge as the north side is demolished and half of the new bridge is built. Once that side is completed traffic will be shifted onto the new Tidal Relief bridge, the south side of the old bridge will be demolished and the second half of the replacement bridge will be built.

Marine traffic will be maintained at all times. The Intracoastal Waterway bridge will continue to open on the quarter-hour and three-quarter hour schedule.

How long will construction take?
Construction is expected to begin in April 2017 with completion anticipated by late 2020.

What will happen to the existing bridge?
The existing bridges will be demolished and removed. The department will evaluate the feasibility of using some portions of the existing bridges as an artificial reef.

How was the new bridge selected?
The PD&E Study considered several alternatives, including low and mid level movable bridges and a fixed high level bridge. These bridge types were analyzed with several horizontal alignment options. The preferred alternative was finalized upon receipt of Location and Design Concept Acceptance (LDCA) by the Federal Highway Administration on May 12, 2009.

What is the total cost of the project?
The current construction cost estimate includes temporary bridge, replacement of the Intracoastal and Tide Relief bridges, adjacent roadway and causeway improvements and is approximately $93,000,000.

What is the status of the project?
The project has been awarded to Johnson Brothers Corporation. They are currently procuring materials for the temporary bridge. Utility owners are relocating their lines off the existing bridge and out of the construction path. Construction is scheduled to begin in April 2017.

Will the project include landscape improvements?
Bold landscaping will be planted within the project corridor following completion of the bridge replacements and associated roadway improvements.

How will the recreation areas on the causeway be impacted by construction?
The recreation areas will remain open to the public during construction with a reduction in the space available for recreational use. Public parking will be relocated when construction affects existing parking areas. The public are prohibited from using any construction zones for recreational use. Construction zones will be identified by signs, barricades and/or fencing.

Will the replacement bridges be larger than the existing bridges?
The replacement bridges will have a wider section in order to accommodate a wider refuge lane or “shoulder” in each direction, as well as wider sidewalks. The number of vehicular lanes will be the same. The replacement bridges will have a higher vertical profile.

What type of temporary bridge will be built? How long will its construction last?
The temporary bridge consists of a pre-fabricated vertical lift steel structure at the navigation channel. The temporary fixed bridge approaches consist of a precast concrete deck supported on steel beams and steel pipe piles. Construction of the temporary bridge is estimated to take 8 to 9 months.

Will the intersection at Flagler Drive and Southern Boulevard change?
The intersection at Flagler Drive will be raised approximately 3 feet in order to connect to the higher bridge profile. A westbound to southbound left turn lane will be added and the southbound to eastbound left turn lane eliminated. All other features of this intersection will remain the same as the existing condition.

Will there be any construction on Flagler Drive?
Construction along Flagler is limited to the area impacted by the geometric changes to the intersection with Southern Boulevard and to drainage system upgrades. These areas extend approximately 400 feet north and south of the intersection.